Description of the Project
The Isle of Grain Project is part of a wider programme of works to expand the capacity of the largest Liquified Natural Gas (LNG) Tank terminal in Europe, located on the Isle of Grain.
The project is being delivered by VINCI Construction subsidiaries including Entrepose Contracting, VINCI Construction Grand Projects and Taylor Woodrow, (EVT). The works involve the engineering, procurement, and construction of 190,000m3 LNG tank on behalf of our Client, National Grid.
Works are scheduled to continue until summer 2025.
1. Scope of Services
Technical support in relation to hydrotest activities:
In autumn 2024, hydrotesting of the LNG Tank is scheduled. In order to complete this test EVT are required to obtain permits for the discharge of 130,000m3 of potable water including agreed for rights of access. A permit to discharge application has been developed and submitted to the Environment Agency. This discrete package of work will involve:
* Engagement with the Environment Agency to update the team on progress.
* Where required, liaise with the EVY project team and their consultants to address queries from the Environment Agency.
* Once the permit has been agreed, brief the EVT project team ...